Case Studies

Case Study: Impact Glass for a South Miami Home's Fixed Windows

| By Ivan Ordaz

This is a write-up of a real job we finished this year: a single-family home in the South Miami area where the owner replaced twelve old fixed windows with laminated impact glass. It wasn’t a whole-house job and it wasn’t complicated, which is exactly why it’s useful. Most of the questions we get from homeowners are about jobs like this one, so here is how it went, step by step.

We don’t publish the owner’s name, the address or what they paid. Everything else below comes from the project record.

What the homeowner needed

The house had three groups of fixed (non-opening) windows that weren’t impact rated:

  • A wide transom unit split by a mullion, 74 by 53 inches overall.
  • Three tall, narrow fixed lites, each 28 by 83 inches.
  • Eight small square lites at the garage, each 13.5 by 13.5 inches.

All twelve openings were glass that would have needed shutters or panels before every storm. The owner wanted them replaced with impact windows so those openings would be protected without anyone putting anything up. The operable windows elsewhere in the house were not part of this contract.

That kind of partial scope is common. Not every homeowner replaces every opening at once, and fixed glass is often the first group people tackle because it’s easy to scope and has no hardware to choose.

Why fixed picture windows, and which ones

Because none of these openings needed to open, we quoted fixed picture windows rather than operable units. A fixed window has no sash, no locks and no rollers, so there is less to wear out and less to adjust after install.

A word of caution here: if a window is in a bedroom, it may be your required emergency exit. Swapping an operable bedroom window for a fixed one can put the room out of code. Our guide to egress requirements in Florida explains what the code asks for. In this house, none of the twelve openings served that purpose.

For the products, we used two lines from Mr Glass, one of the manufacturers we buy from:

  • MG-450 fixed picture window for the transom and the three tall lites. These were the larger openings, so they got the heavier glass makeup: two lites of 3/16” heat-strengthened glass bonded with a 0.090” PVB interlayer.
  • MG-350 PW fixed window for the eight small garage lites, glazed with two lites of 1/8” heat-strengthened glass and the same 0.090” PVB interlayer.

The interlayer is what makes the glass “impact” glass. If the outer lite breaks, the plastic layer holds the fragments together and keeps the opening closed. The small garage lites got the thinner makeup; each one is a fraction of the size of the tall units.

All frames were white aluminum to match the house. Clear glass was specified on this job; the manufacturer also offers Low-E and insulated glass options.

The products we install in Miami-Dade carry approvals for that use. If you want to understand what those approval documents say and how to read them, see our article on NOA certification for impact windows.

From quote to signed contract

The owner first contacted us in November 2025. We priced the three groups as separate line items, so the owner could see each part of the job on its own, and the proposal was accepted in early January 2026.

The proposal covered the whole job for those twelve openings: removal and disposal of the old windows, new wood bucks where needed, installation, and caulking inside and out.

The paperwork before anything was ordered

Impact windows are built to order, so the engineering and the permit come first. On this job, the steps ran in this order.

1. Wind loads

We asked a professional engineer (PE) for the design wind pressures for each opening. The pressure an opening has to resist depends on where it sits on the house, how tall the wall is, and whether it’s near a corner. Those numbers decide which product configuration is allowed in each opening.

2. Final measurements

Our installer re-measured every opening. The proposal is priced from an initial measure; the final measure is what the factory builds to, so it has to be exact.

3. Drawings and approvals

We prepared shop drawings of the openings and had the PE review and stamp them, with the relevant sections of the product approvals marked. That stamped package is what the building department reviews.

4. Permit application and Notice of Commencement

The owner signed the permit application and the Notice of Commencement. We submitted the permit, entered the permit number on the notice, and sent the notice to be recorded with the county. In our process, the recorded notice goes into the permit file before the first inspection.

5. Ordering

With the permit in hand, we ordered the windows. Material lead time is typically 6 to 8 weeks after the permit is approved. If you’re planning around hurricane season, count backward from when you want the windows in, and allow for the drawings and the permit before that.

Installation and inspections

Installation on a job this size is short compared with the paperwork. For each opening, the crew takes out the old window, cleans out the old sealant, sets the wood bucks where needed, anchors the new frame as the approved drawings show, then seals it inside and out.

The permit had three inspections in our sequence:

  1. Notice of Commencement on file. The recorded notice has to be in the permit file first.
  2. Bucks and anchors. The inspector checks the wood bucks and the fasteners before they’re covered with sealant and trim. This is the inspection that confirms the window is attached the way the engineer’s drawing says.
  3. Final. Windows installed, sealed and matching the approved drawings and product approvals.

After the final inspection, we did a final walkthrough with the owner and closed the job.

What a homeowner can take from this job

You don’t have to do the whole house at once. Grouping openings by type (all fixed lites first, operable windows later) keeps a project manageable and easier to budget.

Match glass to the opening. Large lites need heavier laminated glass than small ones. A quote that uses one glass makeup everywhere may be over-built in some openings or under-built in others. Ask your contractor why each opening gets what it gets.

Ask for an itemized proposal. Seeing each group of openings priced on its own makes it easy to understand the job and to phase it if you want to.

Plan around the permit. Impact windows are made to order once the permit is approved, typically 6 to 8 weeks, so the earlier the drawings and permit start, the earlier the windows arrive.

Ask for the product approval for each opening. The approval shows the size and glass each window was tested with, and it is what the inspector checks at the end.

If your home has a similar mix of fixed openings, our impact window replacement service page explains how we handle replacement jobs, and our Miami impact window replacement page covers the area we serve around the city.

Frequently asked questions

Can I replace only some of my windows with impact glass?

Yes. This job replaced twelve fixed openings and left the operable windows out of the contract. Openings you don’t replace stay as they are, so they still need whatever storm protection you use today.

Why does a small window need an engineer?

The wind pressure each opening must resist depends on its position on the house. A PE calculates those pressures and stamps the drawings the building department reviews, so the engineering covers the whole set of openings, small ones included.

Is a fixed impact window cheaper to maintain than an operable one?

There is less to maintain because there are no rollers, locks or balances. You still need to keep the exterior sealant in good condition and clean the glass and frame.

How long does the whole process take?

Plan for the drawings and the permit first. Once the permit is approved, material lead time is typically 6 to 8 weeks, followed by the installation and the inspections. Permit review time varies by building department.

Do you remove the old windows and haul them away?

On this job, yes: removal and disposal of the old windows were included in the proposal. Check that line on any quote you compare.

Get a quote for your home

If you have fixed windows, a transom or garage lites that still need shutters every storm, we can measure them and tell you what each opening needs. Call us at (305) 599-0909 or request a free estimate. We’re in Doral and work across Miami-Dade, Broward and Palm Beach counties.

Tags

case study impact window replacement South Miami Miami-Dade picture windows laminated glass permits